CHICAGO – The Illinois Department of Transportation announced today that repairs to the Addison Street bridge over the Kennedy Expressway (Interstate 90/94), in Chicago, will be completed today, weather permitting, with all lanes reopening this afternoon. The project originally was scheduled to wrap up in September, but construction was accelerated to minimize impacts to local traffic during the ongoing Kennedy Expressway rehabilitation.

“We appreciate the public’s cooperation and patience during construction,” said Illinois Transportation Secretary Gia Biagi. “We are especially proud to finish this project ahead of schedule so you can experience the benefits of an improved Addison Street as quickly as possible.”

To complete permanent lane striping and other minor work, intermittent daytime lane closures will be required at times over the next two weeks. ​ ​

The $1.2 million project consisted of repairing the bridge deck and approaches, replacing expansion joints, installing a new deck overlay, resurfacing and constructing new ADA-compliant sidewalk ramps.

To complete the work, Addison Street was reduced from two lanes to one in each direction, with turning restrictions entering and leaving the expressway, which is under construction as part of a separate $169 million project to rehabilitate pavement and bridges from the Edens Expressway (I-94) junction to Ohio Street. ​ 

Over the next six years, IDOT is planning to improve more than 3,200 miles of highway and nearly 9 million square feet of bridge deck as part of Rebuild Illinois, which is investing $33.2 billion into all modes of transportation. Accomplishments through Year Five of Rebuild Illinois include approximately $16 billion of improvements statewide on 6,541 miles of highway, 686 bridges and 986 additional safety improvements.

For more information on IDOT projects, click here. Find traffic and road conditions at www.gettingaroundillinois.com. You also can follow IDOT on Facebook and X.

 

# # #

 

 

Share

Latest stories

Website preview
Channahon Road in Joliet resurfacing begins May 4
CHICAGO – The Illinois Department of Transportation announced today that patching and resurfacing of Channahon Road (U.S. 6) from Terry Drive to Larkin Avenue (Illinois 7) in Joliet will require intermittent daytime lane closures beginning, weather permitting, Monday, May 4.
illinois-department-of-transportation.prezly.com
Website preview
Resurfacing of Old U.S. 50 east of Lawrenceville underway
EFFINGHAM – The Illinois Department of Transportation announced that the resurfacing of Old U.S. 50 east of Lawrenceville from Business U.S. 50 to Illinois 33 is underway. The $3.6 million dollar project is estimated to be completed by the end of June.
illinois-department-of-transportation.prezly.com
Website preview
Illinois 50 in Peotone resurfacing begins May 1
CHICAGO – The Illinois Department of Transportation announced today that patching and resurfacing of Illinois 50 between Beecher and Wilmington roads in Peotone will require intermittent daytime lane closures beginning, weather permitting, Friday, May 1.
illinois-department-of-transportation.prezly.com

Get updates in your mailbox

By clicking "Subscribe" I confirm I have read and agree to the Privacy Policy.

About Illinois Department of Transportation

Contact

2300 S. Dirksen Parkway Springfield, IL 62764

idot.illinois.gov