9/21/26 UPDATE I-74 and John Deere Road work begins Aug. 24

Work will prepare for interchange reconstruction in 2027

9/21/26 UPDATE: There will be overnight work on westbound I-74 beginning Wednesday, Sept. 23, through the early morning hours of Saturday, Sept. 26. Work during this period will include pavement marking installation for upcoming traffic lane shifts and temporary concrete barrier placement.
​​
​Motorists are urged to use caution when travelling through the construction zone. Please reduce speeds, remain alert for workers and construction equipment, and follow all posted signage and traffic control devices.

MOLINE – The Illinois Department of Transportation announced today that weather permitting, work on the Interstate 74 and John Deere Road (Illinois 5) interchange in Moline will begin Monday, Aug. 24. The work zone is on I-74 from south of 27th Street to north of the Rock River, and on John Deere Road between 16th and 38th streets.

Work will prepare I-74 and John Deere Road for a project to reconstruct the interchange in 2027. Improvements include shoulder reconstruction, drainage work, installation of temporary lighting and Intelligent Transportation Systems upgrades.

Construction will be done in the following phases to maintain traffic and minimize disruptions.

Stage 1

There will be overnight lane closures on portions of I-74 and John Deere Road. At least one lane in each direction will be open at all times. Conducting this work overnight allows construction activities to occur while reducing impacts during peak travel hours.

Stages 2 and 3

Work will transition to daytime operations following completion of Stage 1. During these phases, traffic will continue to be maintained on both I-74 and John Deere Road, but the following temporary ramp closures will be necessary as construction progresses.

  • The ramp from westbound John Deere Road to westbound I-74 toward Iowa will be closed during Stage 2.
  • The ramp from eastbound John Deere Road to westbound I-74 toward Iowa will be closed during Stage 3.

Access for local traffic and emergency responders will be maintained throughout construction, and signed detour routes will be provided whenever ramp closures are in effect. This $8.9 million project will be completed by Nov. 30.

Full construction will begin in 2027 and will include the following improvements:

  • Reconstruct the existing cloverleaf interchange with a diverging-diamond interchange. This interchange will increase safety and mobility by reducing the number of conflict points between vehicles, eliminating the weaving conditions along I-74 and eliminating speed differentials associated with weaving, thus improving operations.
  • Reconstruct I-74 from two to three lanes in each direction between 27th Street and the Rock River. Work includes replacing the bridges over 38th Avenue.
  • Reconstruct John Deere Road from 16th Street to 38th Street.
  • Reconstruct 27th Street from just south of John Deere Road to just north of 38th Avenue.
  • Reconstruct 36th/38th avenues from just west of 27th Street to just east of I-74.
  • Additional improvements include drainage improvements, new signing, new landscaping and adding a shared use path at various locations.

Click here to view more information about the project.

Motorists can expect delays and should allow extra time for trips through this area and be prepared for slow and stopped traffic. To avoid the work area, when feasible, use of alternate routes should be considered. Drivers are urged to pay close attention to changed conditions and signs in the work zones, obey the posted speed limits, refrain from using mobile devices, and be alert for workers and equipment.

Over the next six years, IDOT is planning to improve 7,107 lane miles of highway and 8.4 million square feet of bridge deck as part of Rebuild Illinois, which is investing $33.2 billion into all modes of transportation. Accomplishments through Year Seven of Rebuild Illinois include $25.6 billion of improvements statewide to 24,498 lane miles of highway, 959 bridges and 1,475 additional safety improvements.

For IDOT District 2 updates, follow us on X at @IDOTDistrict2 or view area construction details on IDOT’s traveler information map on GettingAroundIllinois.com.

Map of construction zone. ​
Map of construction zone. ​

 

 

Share

Latest stories

Website preview
Bishop Ford: 159th Street bridge rehab, outbound lane changes begin this week
CHICAGO – The Illinois Department of Transportation announced today that as part of the ongoing rehabilitation and modernization of the Bishop Ford Freeway (Interstate 94) from west of Martin Luther King Drive to 159th Street (U.S. 6), work will begin on the 159th Street bridge over the interstate, weather permitting, Tuesday, Oct. 6. Also, the split-lane configuration of the outbound lanes is scheduled to be removed later this week.
illinois-department-of-transportation.prezly.com
Website preview
Public comment sought on proposed Illinois 3/150 improvements in Randolph County
CHESTER – The Illinois Department of Transportation will hold a public meeting to discuss a study for proposed improvements along Illinois 3/150 in Randolph County. The meeting will be held:
illinois-department-of-transportation.prezly.com
Website preview
Harlem Avenue full closure in Riverside Oct. 19
CHICAGO – The Illinois Department of Transportation announced today that repairs by Canadian National Railroad to the crossing on Harlem Avenue (Illinois 43) south of 26th Street, in Riverside, will require a full closure starting, weather permitting, 9 a.m. Monday, Oct. 19.
illinois-department-of-transportation.prezly.com

Get updates in your mailbox

By clicking "Subscribe" I confirm I have read and agree to the Privacy Policy.

About Illinois Department of Transportation

Contact

2300 S. Dirksen Parkway Springfield, IL 62764

idot.illinois.gov