Kennedy rehabilitation update: Week 24
CHICAGO – The Illinois Department of Transportation announced today that the rehabilitation of the Kennedy Expressway (Interstate 90/94) from the Edens Expressway (I-94) junction to Ohio Street continued to progress the week of August 25. The following are highlights completed during the week:
Week of Aug. 25
- Latex concrete bridge deck preparation and placement.
- Lighting upgrades throughout the corridor.
- Structural concrete and steel repairs on bridge piers and concrete and steel beams under various bridges continues.
- Overhead sign foundation work.
- Painting of structural members of various bridges.
- Saw-cutting, removal, preparation and placement of concrete pavement patches at various locations continues.
- Bridge deck joint removal, forming concrete and placement continues.
- Routing and filling pavement cracks.
- Grooving and sealing various bridge decks.
- Hot mix asphalt paving of bridge approach pavement.
Next week’s work will be focused on pavement milling and patching, asphalt placement, bridge joint demolition forming, bridge deck preparation, pouring of latex concrete decks, overhead sign foundation, anti-graffiti coating placement on retaining walls and permanent pavement striping, opening lanes to traffic north of Addison Street to Pulaski Road. Also, work is happening under the road as well as on it. While you might not see people in the work zone, they could be beneath the road.
The outbound lanes from north of Pulaski Road to the Edens junction reopened last week. The repairs in the section between Addison Street and Pulaski Road continues, with that section reopening after Labor Day.
With the reopening of the north end of the project, 70% of the work scheduled for this construction season will be complete.
As a reminder, to accommodate ongoing bridge rehabilitation and ramp repairs, the following ramps are scheduled to close, starting at 9 p.m., Tuesday, Sept. 2:
- Kimball Avenue ramp to outbound Kennedy, anticipated to reopen in approximately three weeks.
- Outbound Kennedy to Addison Street, anticipated to reopen in approximately three weeks.
Current ramp closures
- Outbound Kennedy to Augusta Boulevard/Milwaukee Avenue, anticipated to reopen mid-October.
- North Avenue (Illinois 64) to outbound Kennedy, anticipated to reopen early September.
- Outbound Kennedy to Armitage Avenue, anticipated to reopen early September.
- Fullerton Avenue ramp to outbound Kennedy and the slip ramp portion to Western Avenue, anticipated to reopen mid-September
- Outbound Kennedy to Kimball Avenue, anticipated to reopen Sept. 3.
- Addison Street to outbound Kennedy, anticipated to reopen Sept. 3.
- Outbound Kennedy to Pulaski Road/Irving Park Road (Illinois 19), anticipated to reopen Sept. 3.
- Outbound Kennedy to Diversey Avenue, anticipated to reopen in mid-September.
Motorists should follow the posted detours.
Additional ramp closures for varying durations will be required to complete the project, which remains on pace for an overall completion by Thanksgiving. Details, schedules and impacts to traffic will be shared in advance, closer to the individual closure dates.
The reversible express lanes will remain open in the outbound direction, with two mainline outbound lanes closed at a time. The reversible mid-gate entrance and exits will remain closed.
All scheduled work is subject to change due to multiple factors, including inclement weather. In that event, schedules will be updated and shared with the public.
The public should expect significant delays and allow extra time for trips through this area. Drivers are urged to pay close attention to flaggers and signs in the work zones, obey the posted speed limits and be on the alert for workers and equipment.
Throughout construction, traveling during non-peak hours, taking alternative routes and utilizing public transportation, including the Chicago Transit Authority’s Blue Line and Metra’s Union Pacific Northwest Line, as well as Pace, are recommended.
For more information, visit https://idot.illinois.gov/projects/Interstate-90-Kennedy-Bridge-Study. The website features project details, maps, photos and fact sheets. The public can email questions to DOT.KennedyRehab@illinois.gov. For systemwide traffic and road conditions, visit www.gettingaroundillinois.com. You also can follow IDOT on Facebook and X.
# # #