U.S. 20 in Jo Daviess County reopens

12-day closure aided in $31.6 million reconstruction project

STOCKTON – The Illinois Department of Transportation announced today that U.S. 20 between the west limits of Stockton and Logemann Road in Jo Daviess County is open following a 12-day closure.

Since the road closed on April 13, workers removed the existing culverts in the area and installed 10 new culverts. The closure was necessary to expedite a $31.6 million road improvement project and minimize any potential traffic disruptions in the work zone over the next two years. With no traffic on U.S. 20, workers were able to perform additional work that would have been subject to multiple daily lane closures such as grading and constructing a barrier wall as part of the new Rush Creek bridge.

This project includes the construction of a new alignment of U.S. 20 north of the current road that will include a truck cl

New dual culverts installed east of Logemann Road. ​

imbing lane and a new bridge over Rush Creek. All of the existing road will be reconstructed along the 4-mile corridor and will include left turn lanes and paved shoulders.

Work in 2026 will mainly be off the existing road and will concentrate on the new alignments at the west and east ends of the project area. Construction in 2027 will be done in sections between Mapes/Golf Roads and Canyon Park/Massbach Roads with one lane of traffic open and controlled by temporary signals. Some side roads will be closed for reconstruction during the project, which is anticipated to be completed in November 2027.

Drivers are urged to pay close attention to changed conditions and signs in the work zone areas, obey the posted speed limits, refrain from using mobile devices and be alert for workers and equipment.

Over the next six years, IDOT is planning to improve 7,107 lane miles of highway and 8.4 million square feet of bridge deck as part of Rebuild Illinois, which is investing $33.2 billion into all modes of transportation. Accomplishments through Year Six of Rebuild Illinois include almost $20.8 billion of improvements statewide to 21,309 lane miles of highway, 815 bridges and 1,181 additional safety improvements.

For IDOT District 2 updates, follow us on X at @IDOTDistrict2 or view area construction details on IDOT’s traveler information map on GettingAroundIllinois.com.

Completion of culvert installation east of Logemann Road.
New culvert installation at Golf Road near U.S. 20.

 

 

Share

Latest stories

Website preview
Lighting to shut off on U.S. 30, U.S. 52 Mississippi River bridges June 12
DIXON – The Illinois Department of Transportation announced today that it will be shutting off the bridge’s roadway lights on the U.S. 52 Mississippi River Bridge (Dale Gardner Veterans Memorial Bridge) in Carroll County and U.S. 30 Mississippi River Bridge (Gateway Bridge) in Whiteside County beginning Friday, June 12.
illinois-department-of-transportation.prezly.com
Website preview
I-270 lane closures scheduled this weekend in Madison County
GRANITE CITY – The Illinois Department of Transportation today announced lane closures on eastbound and westbound Interstate 270 from Illinois 3 to the Mississippi River in Madison County for road construction. Beginning at 9 p.m. Friday, June 5, traffic will be reduced to the right lane in both directions, weather permitting. Two lanes will reopen to traffic by 6 a.m. Sunday, June 7. Motorists should expect delays and are encouraged to use alternate routes during this closure. Drivers are urged to reduce speed, be alert for changing conditions, obey all construction signage and avoid distractions such as mobile devices when approaching and traveling through the work zone.
illinois-department-of-transportation.prezly.com
Website preview
Illinois 13 lane closures at Kaskaskia River Bridge begin June 8 in St. Clair County
NEW ATHENS – The Illinois Department of Transportation today announced that lane closures will be in place on Illinois 13 at the Kaskaskia River Bridge north of New Athens in St. Clair County beginning at 7 a.m. Monday, June 8, weather permitting. The lane closures are required for navigation lighting repairs on the bridge and will be in place during daytime hours. Flaggers will maintain two-way traffic. The work is expected to last three days. Motorists should expect delays and are encouraged to use alternate routes during this closure. Drivers are urged to reduce speed, be alert for changing conditions, obey all construction signage, and refrain from using mobile devices while approaching and traveling through the work zone.
illinois-department-of-transportation.prezly.com

Get updates in your mailbox

By clicking "Subscribe" I confirm I have read and agree to the Privacy Policy.

About Illinois Department of Transportation

Contact

2300 S. Dirksen Parkway Springfield, IL 62764

idot.illinois.gov