Kennedy rehabilitation update: Week 21

CHICAGO – The Illinois Department of Transportation announced today that the rehabilitation of the Kennedy Expressway (Interstate 90/94) from the Edens Expressway (I-94) junction to Ohio Street continued to progress the week of Aug. 4. The following are highlights completed during the week: ​ ​ ​ ​ ​ ​ 

Week of Aug. 4 ​ ​ ​ ​ ​ ​ 

  • Latex concrete bridge deck preparation and placement. ​ ​ ​ ​ 
  • Lighting upgrades throughout the corridor. ​ ​ ​ ​ 
  • Structural concrete and steel repairs on bridge piers and concrete and steel beams under various bridges continues. ​ ​ ​ ​ ​ ​ 
  • Overhead sign foundation work. 
  • Painting of structural members of various bridges. ​ ​ ​ ​ ​ ​ 
  • Saw-cutting, removal, preparation and placement of concrete pavement patches at various locations continues. ​ ​ ​ ​ ​ ​ 
  • Bridge deck joint removal, forming concrete and placement continues. ​ ​ ​ ​ ​ ​ ​ 
  • Routing and filling pavement cracks. ​ ​ ​ ​ ​ ​ 
  • Grooving and sealing various bridge decks. ​ ​ ​ ​ ​ ​ ​ 
  • Hot mix asphalt paving of bridge approach pavement ​ 

Next week’s work will be focused on pavement milling, pavement patching, asphalt placement, bridge joint demolition forming, bridge deck preparation and pouring of latex concrete decks. Also, work is happening under the road as well as on it. While you might not see people in the work zone, they could be beneath the road. ​ ​ ​ ​ ​ ​ ​ 

 

As a reminder, a new traffic configuration approaching the Edens Expressway went into effect this week and will remain in place through the week of Aug. 18 with the work zone reducing the outbound lanes to four lanes, split into two lanes each separated by a barrier wall between Kostner Avenue and the Edens junction. The two left lanes will continue on to the outbound Kennedy (I-90), while the two right lanes will shift slightly to the right and continue to the Edens (I-94). ​ 

The public should be aware of the changes, prepare to merge into their preferred lane early and anticipate some delays during the first few days of the configuration. ​ ​ 

The following ramps are currently closed to accommodate ongoing bridge rehabilitation and ramp repairs: ​ ​ ​ ​ 

  • Outbound Kennedy to Augusta Boulevard/Milwaukee Avenue, anticipated to reopen mid-October. ​ ​ ​ ​ ​ ​ 
  • North Avenue (Illinois 64) to outbound Kennedy, anticipated to reopen early September. ​ ​ 
  • Outbound Kennedy to Armitage Avenue, anticipated to reopen early September. ​ ​ ​ ​ 
  • Fullerton Avenue to outbound Kennedy, anticipated to reopen mid-August. ​ ​ ​ ​ 
  • Outbound Kennedy to Kimball Avenue, anticipated to reopen mid-August. ​ ​ ​ ​ 
  • Addison Street to outbound Kennedy, anticipated to reopen late August. 
  • Outbound Kennedy to Pulaski Road/Irving Park Road (Illinois 19), anticipated to reopen late August. 

 

Additional ramp closures for varying durations will be required to complete the project, which remains on pace for an overall completion by Thanksgiving. Details, schedules and impacts to traffic will be shared in advance, closer to the individual closure dates. ​ ​ 

Motorists should follow the posted detours. ​ ​ ​ ​ 

The reversible express lanes will remain open in the outbound direction, with two mainline outbound lanes closed at a time. The reversible mid-gate entrance and exits will remain closed. ​ ​​ ​ ​ 

All scheduled work is subject to change due to multiple factors, including inclement weather. In that event, schedules will be updated and shared with the public. ​ ​ ​ ​ ​ ​ ​ 

The public should expect significant delays and allow extra time for trips through this area. Drivers are urged to pay close attention to flaggers and signs in the work zones, obey the posted speed limits and be on the alert for workers and equipment. ​ ​ ​ ​ ​ ​ ​ 

Throughout construction, traveling during non-peak hours, taking alternative routes and utilizing public transportation, including the Chicago Transit Authority’s Blue Line and Metra’s Union Pacific Northwest Line, as well as Pace, are recommended. ​ ​ ​ ​ ​ ​ 

For more information, visit https://idot.illinois.gov/projects/Interstate-90-Kennedy-Bridge-Study. The website features project details, maps, photos and fact sheets. The public can email questions to DOT.KennedyRehab@illinois.gov. For systemwide traffic and road conditions, visit www.gettingaroundillinois.com. You also can follow IDOT on Facebook and X. ​ ​ ​ 

 

# # #

 

Share

Latest stories

Website preview
District 2 to hold open house for seasonal employment on Oct. 7 in Milan
DIXON – The Illinois Department of Transportation District 2 will be holding an open house on Tuesday, Oct. 7, in Milan for individuals interested in applying for seasonal positions to help with snow and ice removal in Rock Island County. The event will be held from 3:30 to 6:30 p.m. at the Milan Maintenance Yard, 4128 69th Ave.
illinois-department-of-transportation.prezly.com
Website preview
I-80 interchange at Richards Street reopens Oct. 1
CHICAGO – The Illinois Department of Transportation announced today that as part of ongoing efforts to rebuild Interstate 80 from Ridge Road in Minooka to U.S. 30 in Joliet and New Lenox, the reconstructed interchange at I-80 and Richards Street is nearing completion and is scheduled to reopen by 5 a.m., weather permitting, Wednesday, Oct. 1.
illinois-department-of-transportation.prezly.com
Website preview
Illinois 31 work begins Oct. 6
CHICAGO – The Illinois Department of Transportation announced today that work on Illinois 31 (Western Algonquin Bypass) between North and South Main streets in Algonquin will begin, weather permitting, Monday, Oct. 6. The work will require intermittent daytime and overnight lane closures.
illinois-department-of-transportation.prezly.com

Get updates in your mailbox

By clicking "Subscribe" I confirm I have read and agree to the Privacy Policy.

About Illinois Department of Transportation

Contact

2300 S. Dirksen Parkway Springfield, IL 62764

idot.illinois.gov