Kennedy rehabilitation update: Week 26

The Illinois Department of Transportation announced today that the rehabilitation of the Kennedy Expressway (Interstate 90/94) from the Edens Expressway (I-94) junction to Ohio Street continued to progress the week of Sept. 8. The following are highlights completed during the week: ​ ​ ​ 

Week of Sept. 8 ​ 

  • Latex concrete bridge deck preparation and placement. ​ ​ ​ ​ ​ 
  • Lighting upgrades throughout the corridor. ​ ​ ​ ​ ​ 
  • Structural concrete and steel repairs on bridge piers and concrete and steel beams under various bridges continues. ​ ​ ​ ​ ​ ​ ​ 
  • Overhead sign foundation work. ​ 
  • Painting of structural members of various bridges. ​ ​ ​ ​ ​ ​ ​ 
  • Saw-cutting, removal, preparation and placement of concrete pavement patches at various locations continues. ​ ​ ​ ​ ​ ​ ​ 
  • Bridge deck joint removal, forming concrete and placement continues. ​ ​ ​ ​ ​ ​ ​ ​ 
  • Routing and filling pavement cracks. ​ ​ ​ ​ ​ ​ ​ 
  • Grooving and sealing various bridge decks. ​ ​ ​ ​ ​ ​ ​ ​ 
  • Hot mix asphalt paving of bridge approach pavement. ​ ​ 

 

Next week’s work will be focused on pavement milling and patching, asphalt placement, bridge joint demolition forming, bridge deck preparation, pouring of latex concrete decks, overhead sign installation, anti-graffiti coating placement on retaining walls, drainage structure cleaning and permanent pavement striping. Also, work is happening under the road as well as on it. While you might not see people in the work zone, they could be beneath the road. ​ ​ ​ ​ ​ ​ ​ 

As a reminder, the outbound Kennedy ramp to Diversey Avenue and the Fullerton Avenue slip ramp to Western Avenue are scheduled to reopen, weather permitting, Saturday, Sept. 13.​ ​ 

Current ramp closures: ​ 

  • Outbound Kennedy to Augusta Boulevard/Milwaukee Avenue, anticipated to reopen mid-October. ​ ​ ​ 
  • Fullerton Avenue to outbound Kennedy, anticipated to reopen late September. ​ ​ ​ 
  • Outbound Kennedy to Addison Street, anticipated to reopen late September. ​ 
  • Kimball Avenue ramp to outbound Kennedy, anticipated to reopen late September. 
  • Outbound Kennedy to Damen Avenue, anticipated to reopen in late October. ​ 

 All scheduled work is subject to change due to multiple factors, including inclement weather. In that event, schedules will be updated and shared with the public. ​ 

Additional ramp closures for varying durations will be required to complete the project. Details, schedules and impacts to traffic will be shared in advance, closer to the individual closure dates. ​ 

The public should follow the posted detours. ​ 

The reversible express lanes will remain open in the outbound direction, with two mainline outbound lanes closed at a time. The reversible mid-gate entrance and exits will remain closed. The overall outbound Kennedy project is anticipated to be completed by Thanksgiving, with all lanes and ramps reopening and the express lanes resuming normal operations. ​ ​ 

The public should expect significant delays and allow extra time for trips through this area. Drivers are urged to pay close attention to flaggers and signs in the work zones, obey the posted speed limits and be on the alert for workers and equipment. 

 Throughout construction, traveling during non-peak hours, taking alternative routes and utilizing public transportation, including the Chicago Transit Authority’s Blue Line and Metra’s Union Pacific Northwest Line, as well as Pace, are recommended. ​ 

For more information, visit https://idot.illinois.gov/projects/Interstate-90-Kennedy-Bridge-Study. The website features project details, maps, photos and fact sheets. The public can email questions to DOT.KennedyRehab@illinois.gov. For systemwide traffic and road conditions, visit www.gettingaroundillinois.com. You also can follow IDOT on Facebook and X. ​ 

 

# # #

 

Share

Latest stories

Website preview
Lick Creek Road closure begins Nov. 3
CARBONDALE – The Illinois Department of Transportation today announced that work on the Interstate 57 concrete overlay project in Union and Johnson counties will require an 18-day closure of Lick Creek Road at the I-57 interchange. Northbound and southbound entrance and exit ramps at the Lick Creek interchange will also be closed.
illinois-department-of-transportation.prezly.com
Website preview
Lane closures on I-55/70 in St. Clair County
MADISON – The Illinois Department of Transportation today announced that lane closures will take place on eastbound Interstate 55/70 between Illinois 203 and Exchange Avenue in St. Clair County.
illinois-department-of-transportation.prezly.com
Website preview
Temporary closure of Illinois 163 at Bond Avenue
EAST ST. LOUIS – The Illinois Department of Transportation today announced that rehabilitation of a crossing by Norfolk Southern railroad on Illinois 163 between Bond Avenue and Lakewood Place in St. Clair County will require a full closure beginning, weather permitting, Monday, Nov. 3.
illinois-department-of-transportation.prezly.com

Get updates in your mailbox

By clicking "Subscribe" I confirm I have read and agree to the Privacy Policy.

About Illinois Department of Transportation

Contact

2300 S. Dirksen Parkway Springfield, IL 62764

idot.illinois.gov